Data center due diligence

Know what you are buying before the data center is yours

Data center due diligence is the review that checks whether a facility's power, cooling, building, contracts and history match what you are being shown. Build your scope in two minutes, then send it to our team for a review plan.

Build my scopeRequest a Review

  • For buyers, lenders, developers and large tenants
  • Reply by email within 24 hours
  • Your deal stays confidential
Diligence scopeExample: 12 MW acquisition
Ref DD-EXAMPLE10 weeks to close
  1. 01Utility power and interconnectionIs the 12 MW committed in writing, or only discussed?Critical
  2. 02Electrical systemsDoes the one-line diagram support the 2N claim?Critical
  3. 03Contracts, customers and revenueTwo tenants hold most of the load; both renew in year twoCritical
  4. 04Remaining life and capital planUPS batteries and chillers near replacement ageHigh
  5. 05EnvironmentalPhase I and generator air permitsHigh
  6. 06Network and connectivityThree carriers on site, diverse entry confirmedStandard
6 workstreams about 5 weeks of reviewIllustrative

Scope builder

Scope your diligence in five answers

Pick the deal type, size and timing. The scope ranks each workstream, sketches a timeline against your closing date and lists the deal breakers to look for first.

01What is the deal?
02Is it operating today?
03How large?
04Weeks to close or commit
05Biggest worry so far
Diligence scopePlanning draft
Ref DD-261128Updates as you answer
Deal
Acquiring an operating facility
Size
5 to 20 MW
Review
About 5 weeks

    Rough timeline in weeks

    Deal breakers to look for

      Planning estimate, not a quote

      Why it matters

      Where data center deals go wrong

      Outages are rare but expensive, and most trace back to systems a diligence review can test before closing.

      45%

      of operators' most recent impactful outages in 2025 were caused by power problems.

      Uptime Institute, Annual Outage Analysis 2026
      57%

      of respondents said their most recent major outage cost more than $100,000.

      Uptime Institute, Annual Outage Analysis 2026
      180 days

      before closing is the window for key parts of a Phase I environmental inquiry under the federal rule.

      U.S. EPA, 40 CFR 312.20

      What a review covers

      The workstreams behind a data center decision

      Each one has its own documents and its own ways to fail. The full list, with every item to request, is in the data center due diligence checklist.

      Utility power and interconnection

      Whether the capacity in the pitch is committed by the utility in writing, when it energizes, and who pays for the upgrades.

      Ask forService agreement, will-serve or load letters, one-line diagram, utility correspondence

      Electrical systems

      UPS, generators, transfer switches and switchgear checked against the redundancy being sold, plus test and maintenance records.

      Ask forSingle-line drawings, load bank and IR scan results, maintenance logs

      Cooling and mechanical

      Cooling capacity at design conditions, water source and use, and whether the plant can support the rack densities in the plan.

      Ask forDesign basis, commissioning reports, trend data, water agreements

      Fire and life safety

      Detection and suppression, inspection history and any open code items with the local authority.

      Ask forInspection and testing reports, AHJ correspondence, suppression design

      Building, structure and site

      Roof, floor loading, flood and seismic exposure, zoning that names the use, and permits and certificates of occupancy.

      Ask forProperty condition report, ALTA survey, zoning letter, permits

      Environmental

      A Phase I site assessment, fuel storage, generator air permits and anything that limits expansion.

      Ask forPhase I report, air permits, spill prevention plan, tank records

      Network and connectivity

      Which carriers are on site, whether fiber enters on diverse paths, and who controls the meet-me room.

      Ask forCarrier list, fiber route maps, meet-me room agreements

      Operations and incident history

      Staffing, the maintenance program, outage history and third-party audits such as SOC 2.

      Ask forIncident logs for three years, procedures, audit reports

      Who uses this

      Built for the people signing

      Investors and acquirers

      Buying an operating facility or a platform, and needing the power, equipment and revenue risks priced before the purchase agreement is final.

      Developers and landowners

      Funding or selling a powered site or development, where the utility commitment, zoning and environmental record decide what the land is worth.

      Lenders

      Underwriting a loan against a facility whose value rests on contracts, equipment life and a power position that must hold for the loan term.

      Enterprises committing to a lease

      Signing a multi-megawatt lease and needing proof that the capacity, redundancy and service levels exist before the contract does.

      How a review works

      From your first email to a written answer

      Every engagement is fixed-fee and scoped in writing before work starts. Our technical due diligence guide explains what the engineering side covers.

      1. Send the basics

        Deal type, location, size and dates, with your scope attached if you built one.

      2. Get a review plan

        Within 24 hours: the workstreams to run first and the documents to request from the seller.

      3. Agree a fixed fee

        Scope, deliverables and price in writing. You decide before any work begins.

      4. Receive findings

        A written report ranked by risk, tied to your closing date, with what to renegotiate or walk away from.

      Questions

      Data center due diligence questions

      What is data center due diligence?

      Data center due diligence is the review a buyer, lender, developer or large tenant runs before committing money to a facility. It checks whether the power, cooling, building, contracts and operating history match what the seller or provider is presenting, and prices the risks that do not.

      How is it different from due diligence on an office building?

      The building is a small part of the value. Most of the risk sits in utility power commitments, electrical and cooling systems, equipment life, customer contracts and outage history, so a data center review adds technical and power workstreams that a standard property review does not cover.

      How long does data center due diligence take?

      It depends on size, how quickly the seller shares documents and how many workstreams are critical. Many single-site reviews run several weeks; portfolios and development projects run longer. The scope builder on this page gives a planning estimate for your deal.

      What documents should a buyer request first?

      Start with the utility service agreement or will-serve letters, the electrical one-line diagram, maintenance and test records, the rent roll and customer agreements, the incident log and the most recent Phase I environmental site assessment. The checklist page lists the full set by workstream.

      Does a Phase I environmental assessment have a time limit?

      Yes. Under the federal all appropriate inquiries rule, the inquiry must be conducted within one year before acquisition, and some parts, including interviews, lien searches, records review and the site visit, within 180 days (40 CFR 312.20).

      Who runs this site?

      Data Center Due Diligence is run by Metro Colo Advisory's team. Review requests go to that team, are answered by email within 24 hours, and are not passed to providers or sold.

      Sources

      1. Annual Outage Analysis 2026, Uptime Institute. datacenter.uptimeinstitute.com
      2. 40 CFR 312.20, All appropriate inquiries, eCFR, U.S. EPA rule. www.ecfr.gov
      3. Brownfields All Appropriate Inquiries, U.S. EPA. www.epa.gov
      4. Tier Classification System, Uptime Institute. uptimeinstitute.com

      Have a facility under review?

      Send the deal basics. Our team replies by email within 24 hours with the workstreams we would run first and what to request from the seller.