Data Center
Due Diligence
Request a Review

Home / Due diligence checklist

Checklist

Data center due diligence checklist

45 items across ten workstreams, each with the documents to ask the seller for. Tick items as you go; your progress stays in this browser.

  • Updated November 28, 2026
  • Printable
  • Sources listed at the end

The short answer

A data center due diligence checklist tests whether the facility's power commitment, electrical and cooling systems, building, environmental record, connectivity, operations, contracts and equipment life match what you are being shown. The items that most often change a price are the utility commitment, redundancy as built, customer concentration and deferred capital spending.

0 of 45 done

Utility power and interconnection

6 items

Electrical systems

6 items

Cooling and mechanical

5 items

Fire and life safety

3 items

Building, structure and site

6 items

Environmental

4 items

Network and connectivity

3 items

Operations and incident history

4 items

Contracts, customers and revenue

5 items

Remaining life and capital plan

3 items

What to check first

Work the list in the order risk appears, not the order it is printed. In most acquisitions that means confirming the utility commitment and electrical redundancy in the first week, because both can take months to fix and change what the asset is worth. Revenue items come next for buyers and lenders; environmental items come first for land and development deals. The scope builder ranks these for your deal type, and the technical due diligence guide explains how the engineering items are tested.

Two rules worth knowingUptime Institute's Tier levels run from basic capacity (Tier I) to fault tolerant (Tier IV), and a facility only holds a Tier if it was certified; ask for the certificate. Cooling trend data is easiest to judge against ASHRAE's thermal guidelines for data processing environments.

Questions

What should a data center due diligence checklist include?

It should cover utility power and interconnection, electrical systems, cooling, fire and life safety, the building and site, environmental, connectivity, operations and incidents, customer contracts and revenue, and remaining equipment life. This checklist has 45 items across those ten workstreams, each with the documents to ask for.

Which items should a buyer check first?

Start with the items that can kill a deal: whether utility capacity is committed in writing, whether the electrical design supports the redundancy being sold, customer concentration and renewal dates, and equipment near end of life with no reserve.

How recent does the Phase I environmental assessment need to be?

Under 40 CFR 312.20 the inquiry must be within one year before acquisition, and interviews, lien searches, records review, the site visit and the environmental professional's declaration within 180 days.

Sources

  1. 40 CFR 312.20, All appropriate inquiries, eCFR, U.S. EPA rule. www.ecfr.gov
  2. Brownfields All Appropriate Inquiries, U.S. EPA. www.epa.gov
  3. Tier Classification System, Uptime Institute. uptimeinstitute.com
  4. Datacom Series, Thermal Guidelines for Data Processing Environments, ASHRAE. www.ashrae.org
  5. ISO/IEC 30134-2, Power usage effectiveness, ISO. www.iso.org
  6. NFPA 75, Fire Protection of Information Technology Equipment, NFPA. www.nfpa.org
  7. ANSI/TIA-942 data center standard, Telecommunications Industry Association. tiaonline.org

Have a facility under review?

Send the deal basics. Our team replies by email within 24 hours with the workstreams we would run first and what to request from the seller.

Request a Review